AS 4100 Moment Connection — End Plate & Flange Connection Design

Complete reference for AS 4100:2020 moment-resisting steel connections including bolted end plate (flush and extended), flange welded connections with CJP groove welds, stiffener requirements (Clause 9.5), prying action (Clause 9.3.3.1), and bolt group design for moment transfer. Includes a worked example for a bolted extended end-plate moment connection to a 310UC137 column.

Quick access: Connection Design Calculator | AS 4100 Guide | AS 4100 Connection Design | Bolt Torque Calculator


AS 4100 Moment Connections — Overview

Moment connections transfer bending moment and associated shear between connected members. In Australian practice, moment connections are classified by their rotational stiffness and strength following AS 4100 Clause 9.1.3. The National Construction Code (NCC 2022) references AS 4100 as the primary standard for steel design, and moment connections must satisfy the design requirements of Clause 9 for connections and Clause 5 for member design.

The two most common moment connection types in Australian steel construction are:

Connection Type Stiffness AS 4100 Classification Typical Use
Bolted end plate (flush) Semi-rigid PR or rigid Low-to-medium moment frames
Bolted end plate (extended) Rigid Full-restraint Medium-to-high moment frames, seismic
Welded flange (CJP) Rigid Full-restraint Heavy moment frames, industrial, bridges
Flange plate (bolted) Semi-rigid PR or rigid Field-bolted moment splices
Welded web + bolted flange Semi-rigid PR Composite construction, simple connections
Fin plate with stiffeners Semi-rigid PR Light moment frames, low-rise

AS 4100 Clause 9.1.3.1 requires that connections be classified as either full-restraint (FR) or partial-restraint (PR). For FR connections, the connection must have adequate strength and stiffness to develop the full plastic moment of the connected member. PR connections must account for the rotational stiffness in the structural analysis.


Bolted End Plate Moment Connections

Flush End Plate

A flush end plate has the plate flush with the beam top and bottom flanges. It is typically used for connections where the beam depth does not exceed approximately 600 mm:

Extended End Plate

An extended end plate projects beyond the beam tension flange, allowing additional bolt rows above the flange:

Australian practice follows the AISC End Plate Design methodology adapted for AS 4100 capacity factors and Grade 300 steel. Extended end plates are the dominant moment connection type in Australian steel construction for buildings over 4 storeys.


Moment Connection Design — Bolt Group in Tension

The bolt group in a moment end plate connection is subjected primarily to tension from the applied moment, with the neutral axis located at the compression flange (conservative assumption per Australian practice):

Tension flange force: Tf = Mf* / (d - tf)
Bolt tension per row at tension flange: Nt = Tf / n

where:
  Mf* = design bending moment (N·mm)
  d   = beam depth (mm)
  tf  = beam flange thickness (mm)
  n   = number of bolt rows at tension flange

The neutral axis is taken at the compression flange centreline, which is conservative because it ignores any compression contribution from the web below the neutral axis. The actual neutral axis is approximately at the mid-depth of the beam, which would reduce the tension flange force by about 15-25% depending on the beam depth.

Bolt Tension Design Check (AS 4100 Clause 9.3.3)

Each bolt row is checked against:

Ntf* ≤ phi × 0.80 × fuf × Ac

The bolt force Ntf* must include prying action effects (see below). For extended end plates with bolts outside the tension flange, the outside bolt row carries the largest tension force because of the longer lever arm to the compression flange.


Prying Action in End Plate Design (AS 4100 Clause 9.3.3.1)

Prying action significantly affects bolt tension in end plate connections. AS 4100 uses a T-stub model where the end plate at the tension flange is treated as an inverted T-section loaded by bolts on both sides.

The prying ratio Q is calculated from:

Q = (b/a) × √((Nt-a²)/(Nt-b²) - 1)

where:
  a   = distance from bolt centreline to plate edge
  b   = distance from bolt centreline to flange face
  Nt = applied tension per bolt

When Q > 0 and the plate is sufficiently thick, prying action amplifies the bolt force. When Q is large (> 0.3), the designer should either:

  1. Increase the end plate thickness (reduces deformation and prying)
  2. Reduce the bolt gauge g (brings bolts closer to the flange face)
  3. Add stiffeners between the bolt rows (effective for thick plates > 25 mm)
  4. Increase bolt diameter to provide additional tension capacity

For Australian practice, end plates of 20-25 mm thickness typically control prying to less than 20% amplification for Grade 8.8 M20 bolts. Thinner plates (16 mm) can experience prying amplification of 30-50%, significantly reducing the available moment capacity.


Stiffener Requirements (AS 4100 Clause 9.5)

AS 4100 Clause 9.5 requires stiffeners or continuity plates when the calculated column flange bending capacity is insufficient to resist the beam flange force:

Continuity Plates (Column Flange Stiffeners)

Required when:

Tf > phi × fyc × bfc² × tfc / (3.5 × s)

where:
  Tf  = beam flange force from moment (N)
  fyc = yield strength of column (MPa)
  bfc = column flange width (mm)
  tfc = column flange thickness (mm)
  s   = stiffener spacing = beam flange thickness + 2 × fillet (mm)

If Tf exceeds the column flange bending capacity, continuity plates of minimum thickness matching the beam flange thickness are required. Alternatively, doubler plates may be used on the column web to increase the resistance.

Panel Zone Shear (Column Web at Joint)

The column web panel zone in the joint region must be checked for shear:

Vpz* = Tf - Vcol

where:
  Vcol = column shear at the joint (from frame analysis)

Panel zone shear resistance per AS 4100 Clause 5.10:

phi-Vv = phi × 0.60 × fy × Aw

where:
  phi  = 0.90 (member capacity factor)
  fy   = yield stress of column web (MPa)
  Aw   = column web area = dc × twc (mm²)
  dc   = column web depth (mm)
  twc  = column web thickness (mm)

When Vpz* exceeds phi-Vv, a doubler plate must be welded to the web. In contrast to AISC practice, AS 4100 does not permit panel zone yielding as a ductility mechanism in seismic design — the panel zone must remain elastic under ULS loads.


Welded Flange Moment Connections (AS 4100 Clause 9.7.2)

For heavy moment connections, the beam flanges are connected to the column flange using CJP (complete joint penetration) groove welds:

CJP Groove Weld Design

CJP groove welds are designed as equal to the base metal strength:

phi-Nw = phi × fyf × bf × tf

where:
  phi  = 0.90 (for groove welds)
  fyf  = yield strength of beam flange (MPa)
  bf   = beam flange width (mm)
  tf   = beam flange thickness (mm)

This is identical in principle to the AISC "matched strength" requirement — a CJP weld with matching electrode (e.g., E48XX for Grade 300 steel) is considered to develop the full flange capacity without further calculation.


Worked Example — Bolted End Plate Moment Connection

Problem: Design a bolted extended end plate moment connection between a 530UB92.4 beam and a 310UC137 column. Beam moment demand Mf* = 500 kN·m at the column face.

Design Parameters:

Step 1 — Flange Force: Tf = Mf* / (d - tf) = 500 × 10⁶ / (528 - 15.6) = 500 × 10⁶ / 512.4 = 975,800 N = 976 kN

Step 2 — Bolt Configuration: Extended end plate with 4 rows of M24 bolts:

Assume outside row carries 55% of flange force, inside row carries 45%: Outside bolt tension: Nt = 0.55 × 976 / 4 = 134.2 kN per bolt (each side, 2 bolts per row)

Check with prying (assume Q = 1.15 for 25 mm plate): Ntf* = 1.15 × 134.2 = 154.3 kN per bolt

Step 3 — Bolt Tension Capacity: phi-Ntf = 0.80 × 0.80 × 830 × 353 / 1000 = 187.5 kN per bolt 154.3 kN ≤ 187.5 kN → OK (82% utilisation)

Step 4 — Check Continuity Plates: Beam flange force Tf = 976 kN Column flange bending capacity: phi × fyc × bfc² × tfc / (3.5 × s) = 0.90 × 300 × 309² × 21.2 / (3.5 × (15.6 + 2 × 15)) = 0.90 × 300 × 95,481 × 21.2 / (3.5 × 45.6) = 0.90 × 300 × 95,481 × 21.2 / 159.6 = 0.90 × 300 × 12,681 = 3,423,870 N = 3,424 kN

976 kN ≤ 3,424 kN → Continuity plates not required by strength. However, provided as standard practice for deep beams (530UB).

Step 5 — Panel Zone Shear Check: Column shear (from frame analysis): Vcol ≈ 150 kN Vpz* = Tf - Vcol = 976 - 150 = 826 kN

Web area: Aw = 321 × 13.8 = 4,430 mm² Panel zone shear capacity: phi-Vv = 0.90 × 0.60 × 300 × 4,430 / 1000 = 0.90 × 0.60 × 300 × 4,430 / 1000 = 717 kN

826 kN > 717 kN → Doubler plate required. Required doubler: Add 12 mm plate matching column Grade 300. Total web area with doubler = 13.8 + 12.0 = 25.8 mm → 321 × 25.8 = 8,282 mm² phi-Vv = 0.90 × 0.60 × 300 × 8,282 / 1000 = 1,341 kN > 826 kN → OK

Step 6 — Weld Design: Flange-to-end plate weld: Full-length CJP groove weld with E48XX electrode. Web-to-end plate weld: 8 mm fillet weld, both sides. Shear per web weld: Vf* = 200 kN (from frame analysis) Design capacity per mm: phi × 0.60 × fuw × tt = 0.80 × 0.60 × 480 × 0.707 × 8 / 1000 = 1.30 kN/mm Total web weld length: 2 × (528 - 2 × 15.6) = 2 × 496.8 = 994 mm Capacity: 1.30 × 994 = 1,292 kN > 200 kN → OK

Result: Connection design is acceptable. Extended end plate 25 mm thick, 4 rows × 2 M24 Grade 8.8 bolts, 12 mm doubler plate on column web. Flange CJP weld, 8 mm web fillet welds.


Educational reference only. Verify against AS 4100 and relevant standards. Results are PRELIMINARY — NOT FOR CONSTRUCTION.