Steel Erection Sequence — Planning & Safety

Steel erection is the process of assembling and connecting fabricated steel members into the final structure. The erection sequence affects safety, quality, schedule, and cost. This page covers the planning process, typical sequences, and regulatory requirements per AISC and OSHA.

Erection Planning Overview

Phase Activities Duration
Pre-erection Shop drawing review, sequencing, logistics 2-8 weeks
Foundation prep Anchor bolt placement, grout preparation 1-2 weeks
Erection Lifting, connecting, plumbing, bracing Project-dependent
Bolting Installing, tightening, inspecting bolts Concurrent
Welding Field welding, inspection Concurrent
Decking Installing steel deck, welding studs After framing
Final Final plumbing, touch-up paint, cleanup 1-2 weeks

Typical Erection Sequence for a Steel Building

Step 1: Foundations and Anchor Bolts

  1. Survey anchor bolt locations per the structural drawings
  2. Verify anchor bolt diameter, projection, and embedment
  3. Check template dimensions against column base plate holes
  4. Verify foundation concrete strength (typically 3,000+ psi)
  5. Grout base plates after columns are set and plumbed

Step 2: Columns — First Tier

  1. Erect columns in planned sequence (typically corner columns first)
  2. Install temporary guy wires or bracing for stability
  3. Connect base plates to anchor bolts (snug-tight initially)
  4. Plumb columns using theodolite or laser
  5. Final-tighten anchor bolts after plumbing

Step 3: Beams and Girders — First Tier

  1. Install main girders between columns
  2. Install secondary beams (filler beams) between girders
  3. Install temporary erection bolts (minimum 2 per connection)
  4. Do NOT fully tighten bolts until the tier is plumbed
  5. Check bay diagonals for squareness

Step 4: Bracing and Stability

  1. Install permanent lateral bracing (X-braces, chevron braces)
  2. Install temporary bracing where permanent bracing is not yet in place
  3. Verify the erected portion is self-supporting and plumb
  4. Never leave a partially erected structure unbraced overnight

Step 5: Repeat for Subsequent Tiers

  1. Repeat the column-beam-brace sequence for each floor level
  2. Each tier must be plumb and stable before erecting the next tier
  3. Connections are progressively tightened as each tier is completed

Step 6: Steel Deck and Studs

  1. Install steel floor deck after framing is complete on each tier
  2. Attach deck to beams with puddle welds or screws
  3. Weld shear studs through the deck
  4. Install side lap fasteners between deck sheets

Erection Engineering

Erection engineering ensures the structure is stable during the construction phase, when it is most vulnerable.

Temporary Stability Analysis

Check Requirement
Column stability Cantilever column check during erection
Bracing adequacy Temporary bracing resists wind on partial frame
Connection capacity Erection bolts carry temporary loads
Crane capacity Lift analysis for each member weight and radius
Wind restrictions Stop erection above specified wind speed
Sequencing Each stage must be self-stable

Critical Lifts

Lifts that require special planning:

Lift Type Criteria Required Plan
Standard lift Below crane capacity at radius Lift plan optional
Critical lift > 75% of crane capacity Written lift plan
Super lift > 90% of crane capacity or unusual geometry Engineered lift plan
Tandem lift Two cranes on one piece Engineered lift plan
Night lift Reduced visibility Additional lighting plan

OSHA Requirements for Steel Erection

OSHA 29 CFR 1926 Subpart R governs steel erection safety.

Key OSHA Provisions

Requirement OSHA Standard Details
Training 1926.761 All ironworkers must be trained
Fall protection 1926.760 Required above 15 ft (connectors) or 6 ft (all others)
Multiple lift rigging 1926.753(c)(2) Up to 4 members in single lift (conditions apply)
Hoisting 1926.753 Crane inspections, operator qualifications
Structural integrity 1926.754 Walking/working surfaces must be secured
Bolting 1926.755 Two bolts per connection minimum
Column anchorage 1926.755(b) Columns must be anchored on 4 anchor bolts
Beams and columns 1926.756 Cannot be released until bolted/welded
Flooring 1926.757 Metal decking requirements

Two-Bolt Rule

Every connection must have a minimum of two erection bolts installed before the crane releases the member. This applies to all beam-to-column and beam-to-beam connections. Snug-tight condition is sufficient during erection; final tightening occurs after plumbing.

Column Safety

AISC Code of Standard Practice

The AISC Code of Standard Practice (COSP) defines the responsibilities of the structural engineer, fabricator, and erector.

Key COSP Provisions

Topic Responsibility Standard
Erection drawings Fabricator provides COSP Section 4
Erection sequence Erector proposes, EOR approves COSP Section 7
Temporary bracing Erector designs COSP Section 7.10
Tolerances Per COSP tables COSP Section 7.13
Field connections Erector executes COSP Section 7
Corrections Fabricator/erector per agreement COSP Section 7

Erection Tolerances

Element Tolerance
Column plumb 1/500 × height (approx L/500)
Column offset ±1/8 in per floor, ±1/4 in total
Beam level ±1/8 in from theoretical
Beam alignment ±1/4 in from theoretical
Splice alignment Per AISC COSP Section 7.13

Equipment and Methods

Equipment Capacity Use
Mobile crane 20-300 ton Most building erection
Tower crane 5-20 ton Tall buildings, urban sites
Crawler crane 50-1000 ton Heavy industrial
Cherry picker 1-5 ton Light steel, decking
All-terrain crane 30-200 ton Versatile, rough terrain

Common Rigging Methods

Method Application Notes
Choker hitch Columns, beams Most common
Basket hitch Wide members Two-point pick
Beam clamp Beams with flanges Quick attach/detach
Spreaders Long members Prevents damage to flanges
Lifting lugs Heavy members Shop-welded, engineered

Frequently Asked Questions

What is the sequence of steel erection? The standard sequence is: (1) foundations and anchor bolts, (2) first-tier columns, (3) first-tier beams and girders, (4) permanent bracing, (5) plumb and bolt, (6) repeat for next tier, (7) steel deck and studs. Each tier must be stable before the next begins.

How many bolts are required during erection? A minimum of two bolts per connection must be installed before the crane releases the member. This is an OSHA requirement. For moment connections and heavy members, more bolts may be required by the erection plan.

Who designs the temporary bracing? The erector is responsible for designing and installing temporary bracing. The AISC Code of Standard Practice places this responsibility on the erector. The structural engineer of record (EOR) may provide bracing guidelines but does not design temporary bracing.

How fast is steel erected? A typical steel building erection rate is 10-20 tons per day for a medium-sized crew (8-12 ironworkers) with one crane. Simple structures may achieve 20-30 tons/day. Complex structures with heavy members may be 5-10 tons/day.

Related Pages

Disclaimer

This is a calculation tool, not a substitute for professional engineering certification. All results must be independently verified by a licensed Professional Engineer (PE) or Structural Engineer (SE) before use in construction, fabrication, or permit documents. The user is responsible for the accuracy of all inputs and the verification of all outputs.