Steel Erection Sequence — Planning & Safety
Steel erection is the process of assembling and connecting fabricated steel members into the final structure. The erection sequence affects safety, quality, schedule, and cost. This page covers the planning process, typical sequences, and regulatory requirements per AISC and OSHA.
Erection Planning Overview
| Phase | Activities | Duration |
|---|---|---|
| Pre-erection | Shop drawing review, sequencing, logistics | 2-8 weeks |
| Foundation prep | Anchor bolt placement, grout preparation | 1-2 weeks |
| Erection | Lifting, connecting, plumbing, bracing | Project-dependent |
| Bolting | Installing, tightening, inspecting bolts | Concurrent |
| Welding | Field welding, inspection | Concurrent |
| Decking | Installing steel deck, welding studs | After framing |
| Final | Final plumbing, touch-up paint, cleanup | 1-2 weeks |
Typical Erection Sequence for a Steel Building
Step 1: Foundations and Anchor Bolts
- Survey anchor bolt locations per the structural drawings
- Verify anchor bolt diameter, projection, and embedment
- Check template dimensions against column base plate holes
- Verify foundation concrete strength (typically 3,000+ psi)
- Grout base plates after columns are set and plumbed
Step 2: Columns — First Tier
- Erect columns in planned sequence (typically corner columns first)
- Install temporary guy wires or bracing for stability
- Connect base plates to anchor bolts (snug-tight initially)
- Plumb columns using theodolite or laser
- Final-tighten anchor bolts after plumbing
Step 3: Beams and Girders — First Tier
- Install main girders between columns
- Install secondary beams (filler beams) between girders
- Install temporary erection bolts (minimum 2 per connection)
- Do NOT fully tighten bolts until the tier is plumbed
- Check bay diagonals for squareness
Step 4: Bracing and Stability
- Install permanent lateral bracing (X-braces, chevron braces)
- Install temporary bracing where permanent bracing is not yet in place
- Verify the erected portion is self-supporting and plumb
- Never leave a partially erected structure unbraced overnight
Step 5: Repeat for Subsequent Tiers
- Repeat the column-beam-brace sequence for each floor level
- Each tier must be plumb and stable before erecting the next tier
- Connections are progressively tightened as each tier is completed
Step 6: Steel Deck and Studs
- Install steel floor deck after framing is complete on each tier
- Attach deck to beams with puddle welds or screws
- Weld shear studs through the deck
- Install side lap fasteners between deck sheets
Erection Engineering
Erection engineering ensures the structure is stable during the construction phase, when it is most vulnerable.
Temporary Stability Analysis
| Check | Requirement |
|---|---|
| Column stability | Cantilever column check during erection |
| Bracing adequacy | Temporary bracing resists wind on partial frame |
| Connection capacity | Erection bolts carry temporary loads |
| Crane capacity | Lift analysis for each member weight and radius |
| Wind restrictions | Stop erection above specified wind speed |
| Sequencing | Each stage must be self-stable |
Critical Lifts
Lifts that require special planning:
| Lift Type | Criteria | Required Plan |
|---|---|---|
| Standard lift | Below crane capacity at radius | Lift plan optional |
| Critical lift | > 75% of crane capacity | Written lift plan |
| Super lift | > 90% of crane capacity or unusual geometry | Engineered lift plan |
| Tandem lift | Two cranes on one piece | Engineered lift plan |
| Night lift | Reduced visibility | Additional lighting plan |
OSHA Requirements for Steel Erection
OSHA 29 CFR 1926 Subpart R governs steel erection safety.
Key OSHA Provisions
| Requirement | OSHA Standard | Details |
|---|---|---|
| Training | 1926.761 | All ironworkers must be trained |
| Fall protection | 1926.760 | Required above 15 ft (connectors) or 6 ft (all others) |
| Multiple lift rigging | 1926.753(c)(2) | Up to 4 members in single lift (conditions apply) |
| Hoisting | 1926.753 | Crane inspections, operator qualifications |
| Structural integrity | 1926.754 | Walking/working surfaces must be secured |
| Bolting | 1926.755 | Two bolts per connection minimum |
| Column anchorage | 1926.755(b) | Columns must be anchored on 4 anchor bolts |
| Beams and columns | 1926.756 | Cannot be released until bolted/welded |
| Flooring | 1926.757 | Metal decking requirements |
Two-Bolt Rule
Every connection must have a minimum of two erection bolts installed before the crane releases the member. This applies to all beam-to-column and beam-to-beam connections. Snug-tight condition is sufficient during erection; final tightening occurs after plumbing.
Column Safety
- Columns must have a minimum of 4 anchor bolts
- The column base must be secured before the crane releases
- Double columns (splice above floor level) must be stabilized before the upper column is erected
AISC Code of Standard Practice
The AISC Code of Standard Practice (COSP) defines the responsibilities of the structural engineer, fabricator, and erector.
Key COSP Provisions
| Topic | Responsibility | Standard |
|---|---|---|
| Erection drawings | Fabricator provides | COSP Section 4 |
| Erection sequence | Erector proposes, EOR approves | COSP Section 7 |
| Temporary bracing | Erector designs | COSP Section 7.10 |
| Tolerances | Per COSP tables | COSP Section 7.13 |
| Field connections | Erector executes | COSP Section 7 |
| Corrections | Fabricator/erector per agreement | COSP Section 7 |
Erection Tolerances
| Element | Tolerance |
|---|---|
| Column plumb | 1/500 × height (approx L/500) |
| Column offset | ±1/8 in per floor, ±1/4 in total |
| Beam level | ±1/8 in from theoretical |
| Beam alignment | ±1/4 in from theoretical |
| Splice alignment | Per AISC COSP Section 7.13 |
Equipment and Methods
| Equipment | Capacity | Use |
|---|---|---|
| Mobile crane | 20-300 ton | Most building erection |
| Tower crane | 5-20 ton | Tall buildings, urban sites |
| Crawler crane | 50-1000 ton | Heavy industrial |
| Cherry picker | 1-5 ton | Light steel, decking |
| All-terrain crane | 30-200 ton | Versatile, rough terrain |
Common Rigging Methods
| Method | Application | Notes |
|---|---|---|
| Choker hitch | Columns, beams | Most common |
| Basket hitch | Wide members | Two-point pick |
| Beam clamp | Beams with flanges | Quick attach/detach |
| Spreaders | Long members | Prevents damage to flanges |
| Lifting lugs | Heavy members | Shop-welded, engineered |
Frequently Asked Questions
What is the sequence of steel erection? The standard sequence is: (1) foundations and anchor bolts, (2) first-tier columns, (3) first-tier beams and girders, (4) permanent bracing, (5) plumb and bolt, (6) repeat for next tier, (7) steel deck and studs. Each tier must be stable before the next begins.
How many bolts are required during erection? A minimum of two bolts per connection must be installed before the crane releases the member. This is an OSHA requirement. For moment connections and heavy members, more bolts may be required by the erection plan.
Who designs the temporary bracing? The erector is responsible for designing and installing temporary bracing. The AISC Code of Standard Practice places this responsibility on the erector. The structural engineer of record (EOR) may provide bracing guidelines but does not design temporary bracing.
How fast is steel erected? A typical steel building erection rate is 10-20 tons per day for a medium-sized crew (8-12 ironworkers) with one crane. Simple structures may achieve 20-30 tons/day. Complex structures with heavy members may be 5-10 tons/day.
Related Pages
- Connection Types Explained — All connection types
- Weld Inspection Methods — VT, MT, UT, RT
- Bolted Connections — Bolt capacity calculator
- Steel Weight Calculator — Weight by dimensions
- Base Plate Design — Base plate calculator
Disclaimer
This is a calculation tool, not a substitute for professional engineering certification. All results must be independently verified by a licensed Professional Engineer (PE) or Structural Engineer (SE) before use in construction, fabrication, or permit documents. The user is responsible for the accuracy of all inputs and the verification of all outputs.