Column Splice — Engineering Reference

AISC 360 column splice types: bearing, bolted flange plate, welded. Flange force Pf=Mu/d, bolt/weld sizing, 50% axial minimum. Interactive calculator.

Overview

Column splices connect two column lengths end-to-end, typically located 4 feet above the finished floor level to provide erection clearance and working space. The splice must transfer axial compression, any net tension from load combinations, shear, and moment between the upper and lower shaft. AISC 360-22 Section J1.4 requires that splices in columns designed as part of the lateral-force-resisting system (LFRS) develop at least 50% of the available member strength.

The three common splice configurations are:

Splice type comparison

Type Typical Use Cost Index (1-5) Capacity Field/Shop Seismic OK Size Transition
Bearing (finished) Gravity columns 1 Compression only Field bolts No Same size only
Bolted flange plate LFRS columns 2 Full moment Field bolts Yes (OMF) Width change OK
Bolted web + flange Moment frames 3 Full moment + shear Field bolts Yes (IMF) Moderate change
Welded CJP SMF, heavy columns 4 Full capacity Shop + field Yes (SMF) Requires cap plate
Welded with splice plates Transfer columns 3 Full capacity Shop Depends With filler plates

Splice force requirements

For gravity-only columns (not part of the LFRS), the splice must resist the maximum net tension from factored load combinations and a minimum of the erection stability forces. Per AISC 360-22 J1.4(a), the splice need not develop any percentage of the column capacity if bearing contact is provided and all forces are compressive.

For LFRS columns, the splice must develop at least 50% of the required axial, shear, and flexural strength or the actual required forces, whichever is larger (AISC 360-22 J1.4(b)). In seismic applications per AISC 341, the splice requirements become even more stringent — typically 50% of the expected member capacity (R_y x F_y x A_g / 2 for tension).

The flange force for moment transfer is:

P_f = M_u / (d - t_f)

where d is the column depth and t_f is the flange thickness. Each flange plate or weld group must resist this force plus its share of axial load.

Bolt capacity for splices

Bolt Diameter (in) Single Shear (kip) Double Shear (kip) Bearing on 3/8" plate (kip) Bearing on 1/2" plate (kip)
A325-N 3/4 17.9 35.8 18.4 24.5
A325-N 7/8 24.5 49.0 25.2 33.6
A325-N 1 31.9 63.8 32.6 43.5
A325-X 3/4 22.5 45.0 18.4 24.5
A325-X 7/8 30.8 61.6 25.2 33.6
A490-N 3/4 22.5 45.0 18.4 24.5
A490-N 7/8 30.8 61.6 25.2 33.6
A490-N 1 40.0 80.0 32.6 43.5

Values use phi = 0.75. Bearing assumes F_u = 58 ksi (A36 plate), L_c >= 1.5d.

Flange force by column size

Section d (in) bf (in) tf (in) Pf at Mu=50 kip-ft Pf at Mu=100 kip-ft Pf at Mu=200 kip-ft
W8x31 8.00 7.995 0.435 79.2 kip 158 kip 317 kip
W10x49 9.98 10.0 0.560 63.0 kip 126 kip 252 kip
W12x65 12.12 12.0 0.606 51.8 kip 104 kip 207 kip
W14x48 13.79 8.03 0.595 45.2 kip 90.4 kip 181 kip
W14x61 13.89 10.0 0.645 44.9 kip 89.8 kip 180 kip
W14x68 14.04 10.035 0.720 44.4 kip 88.7 kip 177 kip
W14x82 14.31 10.13 0.855 43.4 kip 86.9 kip 174 kip
W14x90 14.02 14.52 0.710 44.7 kip 89.4 kip 179 kip
W14x109 14.32 14.60 0.860 43.7 kip 87.4 kip 175 kip
W14x120 14.48 14.67 0.960 43.2 kip 86.5 kip 173 kip

Pf = Mu / (d - tf). Deeper columns produce lower flange forces for the same moment.

Minimum splice requirements by system

System Min. Capacity (% Ag Fy) Tension Shear Bolt Type Special Provisions
Gravity column Actual forces only Net tension only Nominal Snug-tight OK Bearing contact sufficient
LFRS column (AISC J1.4b) 50% required strength 50% or actual 50% or actual Snug-tight OK Per J1.4(b)
OMF (AISC 341) 50% Ag Fy 50% Ry Fy Ag Actual SC if tension Bolted or welded
IMF (AISC 341) 50% Ry Fy Ag 50% Ry Fy Ag Actual SC required Demand-critical welds
SMF (AISC 341) 50% Ry Fy Ag (min) Full Ry Fy Ag Actual SC required CJP welds, demand-critical

Filler plate requirements

Filler Thickness AISC Requirement Bolt Impact Development Needed
0 to 1/4 in (0-6 mm) No special requirement None None
1/4 to 1/2 in (6-12 mm) Extend filler beyond splice Moderate reduction Extend + additional bolts
1/2 to 3/4 in (12-19 mm) Must be developed Significant reduction Plated filler or additional bolts
Over 3/4 in (19+ mm) Cap plate preferred Severe reduction Cap plate or built-up solution

Per AISC J5.2: fillers thicker than 6 mm (1/4 in.) must be developed by extending the filler beyond the splice plate and adding bolts, or by using a cap plate.

Size transition details

Transition Typical Example Filler/Cap Required Special Considerations
Same depth, lighter W14x82 to W14x48 Web filler if tw differs Flange width may differ
Width change only W14x90 to W14x68 Flange filler plates Maintain centerline
Depth change (same series) W14x82 to W12x65 Cap plate on lower column Shim web, align one flange
Major change W14x82 to W8x31 Heavy cap plate Eccentricity check required
Heavy to light transition W14x311 to W14x82 Multi-plate buildup Stiffener below cap plate

Worked example — W14x82 to W14x68 splice

Given: Upper column W14x68 (A = 20.0 in^2, d = 14.0 in., b_f = 10.04 in., t_f = 0.72 in.), lower column W14x82. Required forces at splice: P_u = 450 kip (compression), M_u = 120 kip-ft, V_u = 15 kip. Gravity column (not part of LFRS). A36 splice plates, A325-N bolts.

  1. Bearing check: Columns are finished-to-bear. 450 kip compression transfers directly. Bearing capacity = phi x 1.8 x Fy x A_contact. With full-contact bearing, this is satisfied by inspection.
  2. Flange tension from moment: P_f = (120 x 12) / (14.0 - 0.72) = 108.4 kip per flange.
  3. Net flange force: Each flange carries P_u/(2) = 225 kip compression from axial. Net = 225 - 108.4 = 116.6 kip compression on one flange, 225 + 108.4 = 333.4 kip compression on the other. No net tension, so bearing transfers all compression. Provide nominal splice plates for erection stability.
  4. If wind uplift produces P_u = -60 kip (tension): Net flange force = -30 + 108.4 = 78.4 kip tension on the tension flange. Splice plate bolts must resist 78.4 kip. With 3/4 in. A325-N bolts at 17.9 kip/bolt, need 78.4/17.9 = 4.4 -> use 5 bolts per side.

Worked example — moment frame splice (SMF)

Given: W14x82 column, SMF per AISC 341. Upper and lower shaft same size. P_u = 350 kip (compression), M_u = 200 kip-ft, V_u = 25 kip.

Step 1 — Required splice capacity (AISC 341 D2.5b): Min. tension = 0.50 x R_y x F_y x A_g = 0.50 x 1.1 x 50 x 24.0 = 660 kip.

Step 2 — Flange force from moment: P_f = (200 x 12) / (14.31 - 0.855) = 177 kip per flange.

Step 3 — Net flange force (compression side): 350/2 - 177 = -2 kip (net tension possible under uplift combos). Check uplift combo separately.

Step 4 — Flange splice plate design: Required plate area for tension: 660 kip / (phi x F_y) = 660 / (0.90 x 36) = 20.4 in^2. Two flange plates: each 10 in. x 1-1/8 in. = 11.25 in^2 per plate x 2 = 22.5 in^2 > 20.4.

Step 5 — Bolts per flange plate: 660 / 2 = 330 kip per flange. 330 / 22.5 (A490-X 3/4" in double shear) = 14.7 -> 16 bolts (4 rows of 4).

Step 6 — Web splice: V_u = 25 kip. Web splice plate 1/2 in. x 6 in. Two plates. phi x V_n = 1.0 x 0.60 x 36 x 2 x 0.5 x 6 = 129.6 kip >> 25 kip. Use 4 bolts per side.

Splice location guidance

Frame Type Recommended Location Reason Reference
Braced frame 4 ft above floor Low moment region, erection clearance Standard practice
Moment frame Mid-height of story Near inflection point, low moment AISC DG24
Tier building At every tier break Accommodates size transitions Standard practice
Transfer level Above transfer beam Concentrated force location Engineer judgment
Multi-story SMF 4 ft above floor (typ.) Erection clearance, moment capacity check AISC 341

Code comparison — column splice requirements

Parameter AISC 360-22 AS 4100 Cl. 9.1.3 EN 1993-1-8 CSA S16 Cl. 19
Min. strength (LFRS) 50% of required strength Design actions at splice Full design forces 50% of factored resistance
Bearing splice allowed Yes (J1.4a) Yes, with fitted contact Yes, per Cl. 6.2.7.1 Yes, with milled surfaces
Erection bolt minimum 2 bolts per plate Practical minimum 2 bolts Not codified Practical minimum 2 bolts
Seismic splice (SFRS) AISC 341 D2.5b — 50% Ry Fy Ag AS 1170.4 — capacity design EN 1998-1 Cl. 6.5.5 CSA S16 Cl. 27
Filler plate requirements AISC J5.2 — developed if > 6mm AS 4100 Cl. 9.3.2.2 EN 1993-1-8 Cl. 3.6.1 CSA S16 Cl. 22.2

Key design considerations

Common mistakes to avoid

  1. Ignoring the 50% rule for LFRS columns — gravity column splices can be designed for actual forces only, but LFRS columns require 50% of the available strength. Misclassifying a column as gravity-only can produce an under-designed splice.
  2. Forgetting net tension in uplift cases — wind or seismic load combinations frequently produce net column tension. If the splice is designed only for compression bearing, uplift separates the joint. Always check all load combinations for net tension.
  3. Undersized filler plates — when fillers exceed 6 mm (1/4 in.) thickness, AISC J5.2 requires them to be developed by extending the filler beyond the splice plates or by adding additional bolts. Undeveloped fillers reduce the bolt group capacity.
  4. Not detailing for web shear transfer — in moment frame splices, web splice plates are needed to transfer the column shear V_u. Omitting the web splice in a moment frame splice is a common drafting error that can have serious consequences.

Frequently asked questions

What is the 50% rule? AISC 360 J1.4(b) requires that splices in LFRS columns develop at least 50% of the required strength for axial, shear, and flexure. This is a minimum capacity floor, not the actual design forces.

Where should column splices be located? Standard practice is 4 ft above the finished floor. This provides erection clearance and places the splice in a low-moment region for gravity frames.

What is finish-to-bear? Columns machined flat on their ends so they transfer compression through direct steel-to-steel contact. AISC requires flatness within 1/16 in. per 12 in. length.

When do I need filler plates? When the upper and lower column flange widths or thicknesses differ. Fillers over 1/4 in. thick must be developed per AISC J5.2.

Can I weld a column splice in the field? Yes, but field welding requires careful quality control. Demand-critical welds in seismic systems require 100% UT inspection. Bolted splices are preferred for field connections.

What is the difference between a partial and full penetration splice weld? A PJP (partial joint penetration) weld develops only part of the member capacity. A CJP (complete joint penetration) weld develops the full capacity of the connected material. SMF and IMF column splices require CJP welds.

Run this calculation

Related references

Disclaimer

This page is for educational and reference use only. It does not constitute professional engineering advice. All design values must be verified against the applicable standard and project specification before use. The site operator disclaims liability for any loss arising from the use of this information.

Design Resources

Calculator tools

Design guides

Reference pages