Design Shear Resistance — Clause 6.6.3.1
The design shear resistance of a headed stud is the minimum of:
P_Rd = min(0.8 ÃÂàf_u ÃÂàÃÂàÃÂàdÃÂò / 4 / ÃÂó_V, 0.29 ÃÂàÃÂñ ÃÂàdÃÂò ÃÂàâÃÂÃÂ(f_ck ÃÂàE_cm) / ÃÂó_V)
Where:
- f_u = ultimate tensile strength of the stud (âÃÂä 500 MPa)
- d = nominal shank diameter of the stud
- ÃÂó_V = 1.25 (partial factor for shear connectors)
- f_ck = characteristic cylinder compressive strength of concrete
- E_cm = secant modulus of elasticity of concrete
- ÃÂñ = correction factor = 0.2 ÃÂà(h_sc / d + 1) for h_sc/d âÃÂÃÂ¥ 4, or = 1.0 for h_sc/d < 4
The first term represents stud shank failure. The second term represents concrete cone failure.
Stud Resistance Table
Stud Grade — EN ISO 13918 (f_u = 450 MPa typical)
| Stud Diameter | h_sc (mm) | h_sc/d | ÃÂñ | Steel Failure | Concrete Failure (C30/37) | P_Rd (kN) |
|---|---|---|---|---|---|---|
| 19 mm | 100 | 5.3 | 1.0 | 81.4 kN | 69.5 kN | 69.5 |
| 19 mm | 125 | 6.6 | 1.0 | 81.4 kN | 69.5 kN | 69.5 |
| 22 mm | 100 | 4.5 | 1.0 | 109.1 kN | 93.2 kN | 93.2 |
| 22 mm | 125 | 5.7 | 1.0 | 109.1 kN | 93.2 kN | 93.2 |
| 25 mm | 100 | 4.0 | 1.0 | 141.4 kN | 120.3 kN | 120.3 |
| 25 mm | 125 | 5.0 | 1.0 | 141.4 kN | 120.3 kN | 120.3 |
For h_sc/d âÃÂÃÂ¥ 4, h_sc âÃÂÃÂ¥ 4d, ÃÂñ = 1.0 (applies to all standard studs). The concrete failure mode governs for all C30/37 concrete.
Effect of Concrete Grade (22 mm stud, h_sc = 100 mm)
| Concrete Grade | f_ck (MPa) | E_cm (GPa) | P_Rd (kN) |
|---|---|---|---|
| C25/30 | 25 | 31.0 | 80.7 |
| C30/37 | 30 | 33.0 | 93.2 |
| C35/45 | 35 | 34.0 | 104.2 |
| C40/50 | 40 | 35.0 | 114.3 |
| C50/60 | 50 | 37.0 | 133.8 |
Degree of Shear Connection — Clause 6.6.1.2
The degree of shear connection ÃÂ÷ is:
ÃÂ÷ = N_c / N_c,f
Where N_c is the compressive force in the concrete (from the number of shear connectors) and N_c,f is the compressive force at full shear connection (concrete or steel section capacity, whichever is less).
Minimum Degree of Shear Connection
For steel sections with equal flanges and L âÃÂä 25 m:
| Span L | Minimum ÃÂ÷ |
|---|---|
| L âÃÂä 5 m | 0.40 |
| 5 < L âÃÂä 10 m | 0.40 + 0.03 ÃÂà(L - 5) |
| 10 < L âÃÂä 25 m | 0.55 |
For L = 8 m: minimum ÃÂ÷ = 0.40 + 0.03 ÃÂà3 = 0.49.
Worked Example — IPE 300 Composite Beam
| Parameter | Value |
|---|---|
| Beam | IPE 300, S355 |
| Concrete slab | 150 mm deep, C30/37 |
| Effective width | 1500 mm |
| Span | 8.0 m |
| Studs | 19 mm ÃÂÃÂ 100 mm |
Shear Connection Design
| Parameter | Value |
|---|---|
| P_Rd (19 mm, C30/37) | 69.5 kN |
| N_c,f (full connection) | min(A_a ÃÂàf_y / ÃÂó_M0, b_eff ÃÂàh_c ÃÂà0.85 ÃÂàf_ck / ÃÂó_c) |
| A_a ÃÂàf_y / ÃÂó_M0 | 5380 ÃÂà355 / 1.00 = 1910 kN |
| b_eff ÃÂàh_c ÃÂà0.85 f_ck / ÃÂó_c | 1500 ÃÂà100 ÃÂà0.85 ÃÂà30 / 1.50 = 2550 kN |
| N_c,f | 1910 kN (steel governs) |
| Studs for full connection | 1910 / 69.5 = 27.5 âÃÂà28 studs |
| Minimum ÃÂ÷ (L = 8 m) | 0.49 |
| Minimum studs | 0.49 ÃÂÃÂ 28 = 14 studs |
| Provide | 20 studs (2 rows of 10, 200 mm spacing) |
Design decision: 20 studs provides ÃÂ÷ = 20/28 = 71% shear connection, exceeding the minimum 49%. The beam achieves 71% of full composite action, significantly improving stiffness and strength over non-composite design.
Second Worked Example — HE 240A Composite Beam
| Parameter | Value |
|---|---|
| Beam | HEA 240, S355 |
| Concrete slab | 130 mm deep, C30/37 |
| Effective width | 1800 mm |
| Span | 10.0 m |
| Studs | 22 mm ÃÂÃÂ 125 mm |
Shear Connection Design
| Parameter | Value |
|---|---|
| P_Rd (22 mm, C30/37) | 93.2 kN |
| N_c,f (full connection) | min(A_a ÃÂàf_y / ÃÂó_M0, b_eff ÃÂàh_c ÃÂà0.85 ÃÂàf_ck / ÃÂó_c) |
| A_a ÃÂàf_y / ÃÂó_M0 | 7680 ÃÂà355 / 1.00 = 2726 kN |
| b_eff ÃÂàh_c ÃÂà0.85 f_ck / ÃÂó_c | 1800 ÃÂà80 ÃÂà0.85 ÃÂà30 / 1.50 = 2448 kN |
| N_c,f | 2448 kN (concrete governs) |
| Studs for full connection | 2448 / 93.2 = 26.3 âÃÂà27 studs |
| Minimum ÃÂ÷ (L = 10 m) | 0.40 + 0.03 ÃÂà(10 - 5) = 0.55 |
| Minimum studs | 0.55 ÃÂÃÂ 27 = 15 studs |
| Provide | 30 studs (2 rows of 15, 300 mm spacing) |
Design decision: 30 studs provides ÃÂ÷ = 30/27 âÃÂà111% — essentially full shear connection. The stiffer composite section reduces deflection by approximately 40% compared to the bare steel beam.
Stud Welding and Quality Control
Stud Welding Process per EN 14555
Headed shear studs are attached to the steel beam top flange via drawn-arc stud welding (EN 14555). The process uses a ceramic ferrule to contain the weld pool and form the fillet at the stud base.
Key quality requirements:
- Visual inspection: 360-degree weld flash, no undercut > 0.5 mm, stud height after welding within ÃÂñ2 mm of specified h_sc
- Bend testing: Per EN 14555 Annex B, bend studs to 30 degrees from vertical without fracture. At least 1 stud per 100 tested, minimum 2 per beam
- Weld procedure qualification: Per EN ISO 14555, including macro examination of cross-section welds
- Pre-weld surface: Top flange must be free of paint, rust, oil, and mill scale within the stud footprint plus 25 mm perimeter
Stud Placement Through Steel Decking
When studs are welded through profiled steel decking (common in composite slab construction), P_Rd is reduced per EN 1994-1-1 Clause 6.6.4:
Reduction factor k_t: k_t = (0.7 / âÃÂÃÂN_r) ÃÂà(b_o / h_p) ÃÂà(h_sc / h_p - 1) âÃÂä 1.0
Where:
- N_r = number of studs per rib (1 or 2)
- b_o = average rib width
- h_p = overall deck height (âÃÂä 85 mm)
- h_sc = stud height (âÃÂÃÂ¥ h_p + 35 mm)
For decking parallel to the beam, no reduction if the deck is continuous over the beam. For decking transverse, the reduction typically ranges from 0.7 to 0.9 depending on stud-in-rib positioning.
Important: The maximum reduction for studs through decking is k_t ÃÂàP_Rd, and k_t âÃÂÃÂ¥ 0.5 is required for the connection to be classified as ductile per Clause 6.6.1.2(5).
Detailing Requirements — Clause 6.6.5
| Parameter | Requirement |
|---|---|
| Stud height h_sc | h_sc âÃÂÃÂ¥ 4d (âÃÂÃÂ¥ 76 mm for 19 mm stud) |
| Stud spacing long. | min 5d, max 6 ÃÂÃÂ slab depth or 800 mm |
| Stud spacing trans. | min 4d, max 600 mm |
| Cover to stud edge | min 20 mm in solid slab |
| Stud head diameter | âÃÂÃÂ¥ 1.5d |
| Stud head height | âÃÂÃÂ¥ 0.4d |
Frequently Asked Questions
What is the design shear resistance of a 19 mm headed stud in C30/37 concrete per EN 1994-1-1?
The design resistance of a 19 mm ÃÂà100 mm headed stud in C30/37 concrete is P_Rd = 69.5 kN. This is governed by the concrete failure mode (0.29 ÃÂàÃÂñ ÃÂàdÃÂò ÃÂàâÃÂÃÂ(f_ck ÃÂàE_cm) / ÃÂó_V = 69.5 kN) rather than the steel shank failure mode (81.4 kN).
What is the minimum degree of shear connection for composite beams per EN 1994-1-1?
Per Clause 6.6.1.2, the minimum degree of shear connection ÃÂ÷ depends on the span. For spans âÃÂä 5 m, ÃÂ÷_min = 0.40. For spans > 25 m, ÃÂ÷_min = 0.55. Between 5 and 25 m, linear interpolation applies: ÃÂ÷ = 0.40 + 0.03 ÃÂà(L - 5). For an 8 m span, ÃÂ÷_min = 0.49 (49% of full shear connection).
How does stud height affect the design shear resistance? Per the ÃÂñ correction factor (Clause 6.6.3.1(3)), when h_sc/d âÃÂÃÂ¥ 4, ÃÂñ = 1.0 and stud height has no effect on P_Rd. When 3 âÃÂä h_sc/d < 4, ÃÂñ = 0.2 ÃÂà(h_sc/d + 1) âÃÂä 1.0, reducing the concrete failure term. Stud heights below 3d are not permitted. In practice, standard 100 mm studs with 19 mm diameter (h_sc/d = 5.3) operate in the ÃÂñ = 1.0 range.
What is the difference between ductile and non-ductile shear connectors? Ductile connectors (Clause 6.6.1.2) have sufficient deformation capacity to allow redistribution of longitudinal shear between studs at failure. Headed studs with h_sc/d âÃÂÃÂ¥ 4 and 16 âÃÂä d âÃÂä 25 mm are classified as ductile, permitting the use of partial shear connection (ÃÂ÷ < 1.0). Non-ductile connectors require full shear connection (ÃÂ÷ = 1.0) or justification by testing.
Can studs be welded to the underside of the top flange? No. Shear studs must be welded to the top surface of the top flange of the steel beam. Welding to the underside is not permitted because the concrete slab bears on the top flange, and the studs must project into the compression zone of the concrete. Welding to the web or bottom flange provides no composite action.
What happens if stud spacing exceeds the maximum limit? Per Clause 6.6.5.7, the maximum longitudinal spacing is 6 ÃÂÃÂ h_c (slab depth) or 800 mm, whichever is smaller. Exceeding this limit can cause slip concentration and premature failure of individual studs. The minimum spacing (5d longitudinally) ensures adequate concrete between studs to develop the bearing stress.
Related Pages
- Composite Column — CFT per EN 1994-1-1
- EN 1993 Beam Design — Flexural design guide
- European Beam Sizes — IPE, HEA, HEB dimensions
- All European References
Educational reference only. Design per EN 1994-1-1:2004 Clauses 6.6 and 6.7. ÃÂó_V = 1.25. f_u for studs per EN ISO 13918 (typical 450 MPa). Verify stud weld quality per EN 14555. Results are PRELIMINARY — NOT FOR CONSTRUCTION without independent verification.
Design Resources
Calculator tools
Reference pages